- Removal of old panels with complete Isolation during the unit shutdown with provided drawings and sketch.
- Removal of old cable and re rout to the new marshaling and DCS with disconnection drawings.
- Re Installation of the newly designed panels as per layout drawing.
- Re rout the old cable and new cable to the new marshaling and Relay panels as per provided detail drawings.
- Loop checking and commissioning of the signals as per loop drawings and loop check protocol signals details.
- Replacement of old transmitter with new Siemens hart transmitter and its impulse line works, calibration and commissioning.
- Siemens Marshalling and Relay cabinet’s installation, cable pulling, termination and loop testing for the punch list items as per contract.
- Siemens Positioner Sipart link replacement, calibration and commissioning of the control valves as per contracts.
We have been completed the Major up gradation of SIEMENS AG project in Jubail SWCC Phase 2A 2B 10 BTG (Boiler Turbine Generators) and 40 Desalination Plants with complete auxiliary system including two auxiliary boiler together with JC-Eckardt & MAK (Federal Wave Sister Company). The major part of works is removal of old panels and instruments, installation of new field instruments, analyzers, UPS System and DCS panels as follows.
Field Instruments Works carried out as follows:
- Removal and Re installation of Field Instruments like Flow Pressure, Level and Temperatures measurements.
- Removal and re installation of special flow meter MID( Magnetic Flow Meter).
- Removal and re installation of sampling system in Boiler analyzer measurements.
- Removal and re installation of Desal Analyzers and sampling points.
- Removal and Re installation of Capacitance type level measurements in Intake system.
- Commissioning and Startup for Boiler & Water steam (BMS, BPS, FGD, Air Heater System & Lube oil System.
Control Room Panel Works carried out as follows:
- Removal of old panels with complete Isolation during the unit shutdown with provided drawings and sketch.
- Removal of old cable and re rout to the new marshaling and DCS with disconnection drawings.
- Re Installation of the newly designed panels as per layout drawing.
- Re rout the old cable and new cable to the new marshaling and Relay panels as per provided detail drawings.
- Loop checking and commissioning of the signals as per loop drawings and loop check protocol signals details.
In addition to the above are capable to challenging project like new construction project for the filed instrumentation works, control room panel installation and panel internal wiring with high quality and standard works.
Electrical System
Electrical Works carried out as follows:
- Erection and Commissioning of Emerson UPS system manufacture from Chloride France and Turkey.
- Interface the signals between MV switchgear to Siemens T3000 DCS system. Removal of old wiring and re wiring to the new signal as per submitted drawings.
- Interface the signals between LV switchgear to Siemens T3000 DCS system. Removal of old wiring and re wiring to the new signal as per submitted drawings.
- Interface the signals between MCC switchgear to Siemens T3000 DCS system. Removal of old wiring and re wiring to the new signal as per submitted drawings.
- Loop checking and commissioning of the newly interface signals with one by one isolation of the breakers without shutdown the plant.
- We execute the works in electrical MV, LV, MCC and UPS erection, cabling, loop checking and commissioning works.